ActionStep
Place the Cellbag bioreactor on the tray with the optical sensors facing
downwards.
5
NOTICE
Make sure that the optical fiber cables are not placed
between the Cellbag bioreactor and the temperature
sensor on the tray. This could lead to erroneous tem-
perature reading and control, resulting in overheating.
To keep track of the optical fiber cables, mark the cables with the supplied
stickers.
6
Bundle the optical fiber cables on one side of the tray. Fit the lid and make
sure the tubing and cables are placed in the tubing exit. See Illustrations of
tray and lid, on page 47.
7
Connect the pH sensor cable to the pH port on the CBCU front panel.8
Connect the DO sensor cable to the DO port on the CBCU front panel.9
ReadyToProcess WAVE 25 Operating Instructions 29009597 AD 111
5 Operation
5.1 Set up the system
5.1.3 Prepare pH and DO sensors

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE ReadyToProcess WAVE 25 and is the answer not in the manual?

GE ReadyToProcess WAVE 25 Specifications

General IconGeneral
BrandGE
ModelReadyToProcess WAVE 25
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals