4.1.2 Site requirements
Space requirements
Prepare a clean working area on a stable laboratory bench. The bench must fulfill the
following requirements:
Recommended minimum bench space: 80 x 180 cm.
The bench must be clean, level, flat and sufficiently stable to withstand vibration
from the rocking.
Do not place any other vibrating equipment on the same bench, since vibrations
might affect the weight reading.
The bench must be able to support the total weight of the system, including the filled
Cellbag bioreactor. See Equipment dimensions and weight, on page 78. If other op-
tional instruments are installed, their weights must also be included.
Do not place soft material, paper sheets or similar under the system, as this may
block the ventilation inlet.
WARNING
Access to power cord. Do not block access to the power cord. The
power cord must always be easy to disconnect.
76 ReadyToProcess WAVE 25 Operating Instructions 29009597 AD
4 Installation
4.1 Site preparation
4.1.2 Site requirements

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE ReadyToProcess WAVE 25 and is the answer not in the manual?

GE ReadyToProcess WAVE 25 Specifications

General IconGeneral
BrandGE
ModelReadyToProcess WAVE 25
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals