Figure 10-22 Installing the PV input power cables
----End
10.3.4 Installing an AC Output Power Cable
● The live (L) wire and neutral (N) wire of an AC power cable must be correctly
connected.
● The PE wire of an AC power cable must be grounded.
● Do not reversely connect AC output power cables.
A leakage protection device must be congured for the AC output of the
iSitePower-M. The leakage current must be 30 mA. You need to congure and
install the device by yourself.
In single-system scenarios, connect the other end of the cable to the AC load. In parallel-
system scenarios, connect the other end of the cable to the parallel box.
Procedure
Step 1 Connect an AC power cable to the terminal connector.
Figure 10-23 Connecting the cable to the terminal connector
iSitePower-M (MAP05A1, MAB05B1)
User Manual 10 Electrical Connections
Issue 06 (2023-04-24) Copyright © Huawei Digital Power Technologies Co., Ltd. 117