EasyManua.ls Logo

Huawei iSitePower-M MAP05A1 - Installing the Grid Detection Cable of the ATS

Huawei iSitePower-M MAP05A1
221 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Figure 10-47 Installing genset control signal cables
----End
10.5.6 Installing the Grid Detection Cable of the ATS
NO TICE
In the genset-grid scenario, the automatic transfer switch (ATS) must support the
grid detection function. Connect the grid detection cable of the ATS to the dry
contact port DIN1/port DIN2.
Procedure
Step 1 Install the grid detection cable of the ATS.
Figure 10-48 Install the grid detection cable of the ATS
----End
iSitePower-M (MAP05A1, MAB05B1)
User Manual 10 Electrical Connections
Issue 06 (2023-04-24) Copyright © Huawei Digital Power Technologies Co., Ltd. 137

Table of Contents

Related product manuals