Figure 10-62 Installing a PE cable
----End
10.7.2 Installing Input Power Cables for the AC Parallel Box
D ANGER
A surge protective device (SPD) must be congured for the AC input of the
iSitePower-M. You need to congure and install the device by yourself.
Before installing an AC input power cable, ensure that the AC input switch is
turned
o and a prominent label indicating "Do not operate" is set.
AC switches (with a capacity of 40 A) must be installed for phases L and N of
the iSitePower-M AC input. The AC switches are delivered with the iSitePower-
M. Do not use a Type D circuit breaker because it cannot
eectively protect
products.
No leakage protection device is required for the AC input of the iSitePower-M.
If a leakage protection device is
congured, it is recommended that the leakage
current be greater than or equal to 100 mA x
n
, where
n
is the number of
power modules.
CA UTION
The live (L) wire and neutral (N) wire of an AC power cable must be correctly
connected.
The PE wire of an AC power cable must be grounded.
Do not reversely connect AC input power cables.