10.5.7 (Optional) Installing a Communications Cable
Step 1 Connect the network cable to the FE1 port of the product.
Figure 10-49 Installing a communications cable
----End
10.6 PV+Mains+Genset+ESS
10.6.1 Installing Ground Cables
Precautions
D ANGER
Ensure that the ground cable is securely connected. Otherwise, electric shocks may
occur.
Procedure
Step 1 Install ground cables.