11 System Commissioning
D ANGER
Wear personal protective equipment and use dedicated insulated tools to avoid
electric shocks or short circuits.
CA UTION
During the power-on procedure, power o the batteries immediately if any
fault is detected. Rectify the fault before proceeding with the procedure.
After batteries are used for system commissioning or batteries have discharged,
charge the batteries in time. Otherwise, batteries may be damaged due to
overdischarge.
Battery overdischarge and damage may occur if batteries with low SOC are
stored. Batteries should be recharged in a timely manner.
NO TICE
Before the equipment is put into operation for the rst time, ensure that the
parameters are set correctly by professional personnel. Incorrect parameter
settings may result in noncompliance with local grid connection requirements and
aect the normal operations of the equipment.
iSitePower-M (MAP05A1, MAB05B1)
User Manual 11 System Commissioning
Issue 06 (2023-04-24) Copyright © Huawei Digital Power Technologies Co., Ltd. 164