Step 2 Install the AC output power cable and secure the cable using cable clips.
Figure 10-24 Installing the AC output power cable
----End
10.3.5 Installing an AC Input Power Cable
D ANGER
A surge protective device (SPD) must be congured for the AC input of the
iSitePower-M. You need to congure and install the device by yourself.
Before installing an AC input power cable, ensure that the AC input switch is
turned
o and a prominent label indicating "Do not operate" is set.
AC switches (with a capacity of 40 A) must be installed for phases L and N of
the iSitePower-M AC input. The AC switches are delivered with the iSitePower-
M. Do not use a Type D circuit breaker because it cannot
eectively protect
products.
No leakage protection device is required for the AC input of the iSitePower-M.
If a leakage protection device is
congured, it is recommended that the leakage
current be greater than or equal to 100 mA x
n
, where
n
is the number of
power modules.
iSitePower-M (MAP05A1, MAB05B1)
User Manual 10 Electrical Connections
Issue 06 (2023-04-24) Copyright © Huawei Digital Power Technologies Co., Ltd. 118