Figure 10-70 Connecting a remote EPO cable
10.10 Installation Verication
10.10.1 Verifying the Installation
Table 10-1 Check items and acceptance criteria
No.
Check Item Expected Result
1 Product installation The installation is correct and reliable.
2 Cable routing Cables are routed properly as required
by the customer.
3 Cable bonding Cable ties are evenly distributed and no
burr exists.
4 Grounding Power cables, signal cables, and PE
cables are correctly and securely
connected.
5 Switches The DC SWITCH and all switches
connected to the product are OFF.
6 Short circuit at AC
input and output ports
The live (L) wire and neutral (N) wire
of an AC power cable are correctly
connected.
7 Unused terminals and
ports
Unused terminals and ports are locked
by waterproof glands.
8 Removal wrench The removal wrench is placed in the
original position in the decorative cover.
iSitePower-M (MAP05A1, MAB05B1)
User Manual 10 Electrical Connections
Issue 06 (2023-04-24) Copyright © Huawei Digital Power Technologies Co., Ltd. 159