Assembling the JG2 Terminal and Power Cable
Bacnground
Figure 4-88 shows the components of a JG2 terminal and a power cable.
Figure 4-88 Components of a JG2 terminal and a power cable
A. Heat shrink
tubing
B. JG2 terminal C. Insulation layer
of a power cable
D. Conductor of a
power cable
Procedure
1. Strip a part of the insulation to expose the cable conductor with a length of L,
as shown in Figure 4-89. The recommended values of L are listed in Table
4-20.
Figure 4-89 Stripping a power cable (JG2 terminal)
HUAWEI NetEngine 8000 F
Hardware Guide 4 Hardware Installation and Parts Replacement
Issue 05 (2023-03-31) Copyright © Huawei Technologies Co., Ltd. 449