Install the Dual Touch Monitor 223
User Guide v 1.0 — February 2020 Maintenance
9. If necessary, remove the lock out equipment and tag from the main power switch.
10. Energize the system at the main power switch.
15.4.6 Install the Dual Touch Monitor
To install the dual touch monitor, do the steps that follow:
1. If necessary, de-energize the system at the Altanium main power switch. Refer to
Figure 15-2.
2. If necessary, lock out and tag the main power switch in accordance with local codes.
IMPORTANT!
Because of the options purchased and the configuration of your controller there may be
more connectors to connect. Refer to the cable connections in Table 13-6 for a full list of
possible connectors.
Figure 15-36 Dual Touch Monitor Install
WARNING!
Electrical and mechanical hazard- risk of death, serious injury and/or damage to the
equipment. Turn off all power to the system and disconnect it completely from the
main input power.