Performing maintenance
5.
Cleanliness values will be
displayed during the flushing
procedure.
These measurements are not
correct, but should decrease
during the flushing procedure.
6.
Once the 0.5 liters have been
sucked up, switch off the pump.
7.
The FCU flushing procedure is
complete. The FCU is ready for
operation.