Table 44: Site Preparaon Checklist
(Connued)
Item or Task For More Informaon Performed by Date
Select the type of rack or cabinet and
verify that it meets the minimum
requirements for the installaon of the
switch.
"Rack Requirements" on page
132
"Cabinet Requirements" on page
133
Plan rack or cabinet locaon, ensuring the
required space clearances.
"Clearance Requirements for
Airî™™ow and Hardware
Maintenance for an EX9214
Switch" on page 128
Secure the rack or cabinet to the î™™oor
and building structure.
Cables
Plan the cable roung and management.
Acquire cables and connectors:
• Determine the number of cables
needed based on your planned
conguraon.
• Ensure that the distance between
hardware components to be
connected allows for cable lengths to
be within the specied maximum
limits.
119