116 Parallel Operations
9.2.6 Reset Multi-channel Synchronized operation
Set the Master unit to [NORM] as follow.
Push “F1” key Push “F3” key
Push “F3” key Push “F3” key Push “ENT” key
Push “MENU” (or “CE”) key
Slave unit
When reconfigure from Multi-channel Synchronized operation to normal operation, turn all the
power OFF the remove BOOSTER cables.
Turn off the power from the higher slave numbered unit.
In case of turning off all units, or setting the MASTER unit as single operation,
you set all units as single operation ( set [NORMAL] mode on the menu page 1).