Maintenance work on the carrier
7.16 Central lubrication system
7 - 116 3 302 364 en Maintenance manual
GMK 4100L-1
25.11.2016
Topping up
There are various options for filling the grease
container (4):
• Switch on the ignition.
S
Risk of damage to the central lubrication system.
Cleanliness is of the utmost importance when handling grease and
filling p
umps.
Do not remove the caps from the connections and the filling pump until
immediately before refilling the grease, as the grease could otherwise
become contaminated. This prevents dirt particles from getting into the
grease and damaging the central lubrication system. Do not overfill the
container above the max. mark.
1 Grease nipple (standard)
for connection of a manual grease gun.
GROVE part no. 04158709
2 Filling coupling plug (optional)
for connecting a the hose to a grease
filling station with a drum.
GROVE part no. 04165389
3 Filler connection (optional)
for the filling pump from the tool set.
To use this, the plug (3) must be
removed and the filler connection
from the tool box inserted in its place.
GROVE part no. 04165390

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK 4100L-1 and is the answer not in the manual?

Manitowoc Grove GMK 4100L-1 Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK 4100L-1
CategoryConstruction Equipment
LanguageEnglish

Related product manuals