Maintenance work on the carrier
7.17 Electrical system
25.11.2016
Maintenance manual 3 302 364 en 7 - 125
GMK 4100L-1
7.17.5 Check the external starting socket
The battery box is equipped with an external starting socket (1).
Accessories
A connection cable (1) for the ex
ternal starting socket is supplied with the
truck crane (tool set).
The battery box can also be equipped with a battery charger as additional
equipm
ent.
• Consult the operating instructions supplied with the battery charger and
regularly check that all components are functioning correctly to ensure
that the external starting socket, connecting cable and battery charger are
ready for operation if needed;
à Operating Instructions.
Checking
• Remove the cap (4) from the socket (1).
• Check that the cap is not damaged and is
secured with the chain (3).
• If necessary, clean the poles (2).
• Attach the cap – the cap must be fitted
tightly and compactly on the socket.
M 3
Designation GROVE part no.
Connecting cable with two plugs;
Length 12 m
03143281

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK 4100L-1 and is the answer not in the manual?

Manitowoc Grove GMK 4100L-1 Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK 4100L-1
CategoryConstruction Equipment
LanguageEnglish

Related product manuals