Chapter 3: Management with the Promise Utility
37
4. Click the Confirm button.
5. Click the X icon to close the background activities panel.
Synchronization
Synchronization is automatically applied to logical drives when they are created.
Synchronization recalculates the redundancy data to ensure that the working
data on the physical drives is properly in sync.
Mouse-over on the logical drive, click the View button, and look under Logical
Drive Information beside the line that says Synchronized. A Yes means the
logical drive was synchronized. See “Viewing Logical Drive Information” on
page 58.
Making Synchronization Settings
To make Synchronization settings:
1. From the Admin menu, choose Background Activities.
2. Click the Settings button.
3. Click the Background Synchronization Rate dropdown menu and choose
a rate:
• Low – Fewer system resources to Synchronization, more to data read/
write operations.
• Medium – Balances system resources between Synchronization and
data read/write operations.
• High – More system resources to Synchronization, fewer to data read/
write operations.
4. Click the Confirm button.
5. Click the X icon to close the background activities panel.