SPIROR HP - DR
All safety devices must be integral and efficient.
The machine must be cleaned and in order.
Compressed air supply must be open and pressure adjusted to 6 bar.
The film reel must be sufficiently full to guarantee operations (See "Coil replacement").
The film must not be blocked in the clamp (See "Inserting the film into the gripper").
The rotating ring must be in phase (see “Timing of the rotating ring”).
Turn main switch in pos. "I".
Follow the indications displayed.
When the main page is displayed, the machine is ready to perform the operation after pressing the Start
button (See “Commands description”).
Note
At first start up after a change of operation, it is necessary to perform some trial cycles to check the quality of
the wrapping operation.
6.9.1.PUTTING THE ROTATING RING IN PHASE
he machine does not operate and does not block the film in the clamp if the rotating ring is no
in phase.
With the rotating ring in any position, pressing the Reset button will align the ring instead of starting the
operation.
Work can then be started.
6.9.2.FILM SPOOL LOADING
For any model
1. Display the main page.
Touch the key (A) to access the manual
movements (see section “Description of
the operating terminal” - “Description of
manual controls”).
2. Touch the wheel (B) key to enable it and
then the "reel" key (C).
The reel unit will move in front of the
door (D) automatically.