3 PREPARING THE GAS DUCT SIDE
3.3 Installing the connection unit
Fig. 5: Connection unit
Line lengths to the GM32 sender/receiver unit according to project planning.
Provide threaded bolts (4) to screw on the connection unit and screw on the connection
unit, see “Connection unit (all dimensions in mm)”, page 77.
!
Do not make the electrical connection to the connection unit yet.
3.4 Installing the purge air unit (for GMP probe)
Length of the purge air hose to the GM32 according to project planning
Installing the purge air unit Operating Instructions of purge air unit.
NOTE: Adequate purge air pressure
Make sure the purge air supply is sufficiently dimensioned to press the purge air into
the gas duct.
If required, please contact SICK Customer Service or your local representative.