18.6.1 1. Documenting startup
Precondition
As a minimum, the machine name/No., the customer No. and the country where the
manufacturer is located must be entered into the machine identity.
Procedure
1. The machine-specific information data are entered.
2. Start-up (commission) the machine.
3. Press the "1st startup completed" softkey.
The "1.SETUP" entry is displayed in the "Machine logbook" window to‐
gether with the time and date.
Note
2. Perform commissioning
On completion of first commissioning, you will be prompted to perform the 2nd commissioning.
If the 2nd commissioning is not performed, then you will be prompted at regular intervals to
complete the 2nd commissioning.
See also
Entering machine-specific information (Page 428)
18.6.2 2. Defining start-up
Precondition
As a minimum, the country of the end customer must be entered into the machine identity.
Procedure
The machine-specific information data are entered.
2. Start-up (commission) the machine.
3. Press the "2nd startup completed" softkey.
The "2.SETUP" entry is displayed in the "Machine logbook" window to‐
gether with the time and date.
Service and diagnostics
18.6 Logbook
SINUMERIK Operate (IM9)
Commissioning Manual, 12/2017, 6FC5397-1DP40-6BA1 437

Table of Contents

Other manuals for Siemens MCP 398C

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens MCP 398C and is the answer not in the manual?

Siemens MCP 398C Specifications

General IconGeneral
BrandSiemens
ModelMCP 398C
CategoryControl Systems
LanguageEnglish

Related product manuals