Installation and commissioning
4.3 Commissioning the TIM
TIM DNP3
70 System Manual, 12/2015, C79000-G8976-C253-04
4.3
Commissioning the TIM
4.3.1
Steps in commissioning
Requirements for commissioning
The following requirements must be met for the full commissioning of the TIM:
Installation and wiring
Installation and wiring is described in the preceding sections.
Full configuration
The configuration of the TIM is described in the following sections:
Configuration in STEP 7 (Page 77)
The SINAUT Configuration Tool (Page 139)
Steps in commissioning
Commissioning involves the following steps:
1. Turn on the common power supply of the fully wired S7 station.
The LED display during startup is described in the two following sections.
2. Download the configuration data to the station.
Downloading the configuration data is described in the following section:
Downloading (Page 239)
4.3.2
Startup activities of the TIM 3V-IE DNP3
Introduction
During startup, the LEDs on the front panel of the TIM 3V-IE DNP3 have a different
significance compared with normal operation. They are optical indicators of the various
startup phases and provide detailed information about any errors detected during startup.
The only exceptions are the LINK and RX/TX LEDs that have no significance during the
startup of the TIM 3V-IE DNP3.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMATIC TIM 3V-IE DNP3 and is the answer not in the manual?

Siemens SIMATIC TIM 3V-IE DNP3 Specifications

General IconGeneral
BrandSiemens
ModelSIMATIC TIM 3V-IE DNP3
CategoryControl Unit
LanguageEnglish

Related product manuals