Commissioning
SIRIUS 3RW44 manual
5-4 GWA 4NEB 535 2195-02 DS 06
5.2 Switching on for the First Time
Warning
Before switching the device on for the first time, verify that the main/control
side is wired properly. Make sure that the line and control voltage comply with
the device-specific requirements (Chapter 10.3 "Technical Data").
5.2.1 Recommendation on Procedure for 3RW44 Commissioning
Notice
This table provides example set values. They are intended informational purposes only
and are non-binding. The set values depend on the particular application and must be
optimized during commissioning.
Suggested setting
Starting parameters Stopping parameters
Starting mode: Voltage ramp and current limiting
(U+current limiting)
Stopping mode Parameter
Start
voltage
%
Starting
time s
Current
limiting
value
Breakaway pulse
Stopping
time s
Stopping
torque
%
Application
Conveyor belts 70 10 deactivated deactivated (0 ms) Torque control 10 10
Powered roller
conveyors
60 10 deactivated deactivated (0 ms) Torque control 10 10
Compressors 50 10
4xI
e
deactivated (0 ms) Coasting down X X
Small ventilators 30 10
4xI
e
deactivated (0 ms) Coasting down X X
Pumps 30 10
4xI
e
deactivated (0 ms) Pump stop 10 10
Hydraulic pumps 30 10
4xI
e
deactivated (0 ms) Coasting down X X
Stirrers 30 30
4xI
e
deactivated (0 ms) Coasting down X X
Centrifugal machines 30 30
4xI
e
deactivated (0 ms) Coasting down X X
Milling machines 30 30
4xI
e
deactivated (0 ms) Coasting down X X
Large fans 30 60
4xI
e
deactivated (0 ms) Coasting down X X
Mills 50 60
4xI
e
80 % / 300 ms Coasting down X X
Crushers 50 60
4xI
e
80 % / 300 ms Coasting down X X
Circular saws/ribbon
saws
30 60
4xI
e
deactivated (0 ms) Coasting down X X