www.stryker.com 72-1048E MM FL23SE REV A 19
Return To Table of Contents
MAINTENANCE PROCEDURES
WARNING
Always unplug the bed power cord when cleaning or servicing the bed.•
To prevent injury when working under the bed with the bed in the high position, always place blocks under the Hi-Lo •
levers and apply the brakes. Always unplug the bed power cord from the wall outlet when servicing or cleaning the
bed.
STATIC DISCHARGE PRECAUTIONS
The electronic circuits of the bed are protected from static electricity damage only while the bed is assembled. It is
extremely important that all service personnel always use adequate static protection when servicing the electronic
components of the bed.
STATIC PROTECTION EQUIPMENT
The necessary equipment for a proper static protection is:
1 static wrist strap •
1 grounding plug •
1 test lead with a banana plug on one end and an alligator clip on the other.•
STATIC PROTECTION PROCEDURE
Unplug the bed power cord from the wall outlet. 1.
Insert the grounding plug into a properly grounded hospital grade wall receptacle. Plug the banana plug of the test 2.
lead into the receptacle on the grounding plug. Connect the alligator clip on the other end of the test lead to a
ground point on the bed.
Place the static control wrist strap on your wrist. Connect the clip at the other end of the wrist strap cord to a ground 3.
point on the bed.