4 Repair
4.3.3. Replacement of complete arm system
3HAC027151-001 Revision: B174
© Copyright 2006-2008 ABB. All rights reserved.
10. Refit the cabling in the base. Detailed in section Replacement of cable
harness, lower end (axes 1-2) on page
153.
11. Perform a leak-down test of the gearbox axis
1.
Detailed in section Performing a leak-
down test on page 148.
12. Refill the gearbox axis 1 with lubricating oil. Detailed in section Oil change, gearbox
axis 1 on page 126.
13. Recalibrate the robot. Calibration is detailed in a separate
calibration manual, enclosed with the
calibration tools.
General calibration information is
included in section Calibration informa-
tion.
14.
DANGER!
Make sure all safety requirements are met
when performing the first test run. These are
further detailed in section DANGER - First
test run may cause injury or damage! on
page 33.
Action Note
Continued

Table of Contents