1.5.1 Turning On the Power for the First Time
It will take at most 30 minutes for the instrument to complete warm-up and priming.
1 Turn on the main power switch.
a Press the “ – ” side of the main power switch.
2 Turn on the standby switch.
a Open the transparent cover and press the standby switch.
The standby switch will light up orange when power is turned on.
A few seconds later, the switch will turn green and the instrument
will start warm-up.
b Close the transparent cover.
Be sure to close the cover to prevent accidental operation.
Priming will start when the warm-up is complete.
c Wait for the standby screen to appear.
The message “Ready for measurement” and a light green circle
( ) will appear.
NOTE:
Check that eluents A, B and CV, and the hemolysis washing solution are all set before turning on the power.
Standby switch
Ready for measurement
10-06-2010 10:00
Measurement start number 0001
Measurement : Variant
Column 0000
ABCH
Menu Meas No. Priming Cal
Standby screen