4.1 Unpacking
1. Place the packed goods near the installation
location.
i Use an appropriate fork lift or a pallet truck (with
a minimum load capacity of 400kg) to move the
packed machine. Insert the forks between the
support legs of the palette and lift the packaging.
2. Remove the strap and retaining clamps from the
pallet and the packaging carton.
3. Carefully lift off the packaging.
4. Take the standard accessories and the packaging
material out of the transport crate.
i Check if the MT ZERO 6 LCD and the accessories
are in proper working order and that there are
no visible signs of component damage. In case of
doubt, do not commission the device and consult
customer service.
i Dispose of the packaging material at an appropriate
collection site.
4.2 Transporting an handling the wheel
balancing machine
i On delivery, the machine is fastened to the pallet.
651127-08_BM
Fig. 6: MT ZERO 6 LCD on pallet
1. Remove fastening screws.
2. Move the machine from the pallet to a suitable
position intended for installation.
i At least 2 people are needed for this job.
! Do not lift the machine for transport by the shaft
or measurement system. That area must not be
subjected to impacts or potential damage.
651127-01_BM
Fig. 7: Places by which the machine must not be lifted for
transport
! Do not hold the machine by the plastic covers
for moving or lifting. Otherwise, there is a risk of
damage during handling or transport.
3. Carefully position the first side of the machine and
make sure that the machine is in balance and cannot
tip over.
651127-02_BM
Fig. 8: First step of setup
4. Pull out the pallet from under the machine, and
position the machine carefully.
651127-03_BM
Fig. 9: Second step of setup
en
4. Initial commissioning