Nodal commissioning 6-9
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Procedure 6-4 (continued)
Verifying the serial numbers of the 6200 chassis and the circuit packs
Action
Step Action
1 Click Inventory in the Navigation menu.
2 Click on Node inventory link.
Node inventory page is displayed.
3 View the serial numbers of all the circuit packs in the 6200 network element
in the Node Inventory page.
4 Verify the serial numbers of all the circuit packs with the shipment report.
5 Verify that the two PSU circuit packs are listed with the correct information in
the WUI Inventory application.
6 Click Node Slot View under System in the Navigation menu.
Node Slot View page is displayed.
7 Verify that the Power LED is turned on with green color for the two PSU circuit
packs.
—end—