5-1
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Installing the 6200 network element 5-
This chapter contains all the procedures for installing the following:
• the 6200 network element
• peripheral cables
• traffic cables
The 6200 system is available in one variant:
• Normal system compliant to ETSI EN 300 019-1-3 V2.1.2 CLASS 3.1
standard
Installation guidelines
The installation guidelines for the 6200 network element are as follows:
• Ensure that the rack is firmly fixed to the ground.
• Ensure proper grounding of the rack.
• Ensure that the weight of the equipment does not make the rack unstable.
• Ensure that minimum clearance between the two posts of the rack is
450mm when you are mounting the equipment on a rack.
• Ensure that the DC and the AC power supply requisites are satisfied.
— For the base chassis power supply: The input supply voltage is in the
range -40 V to -72 V for DC PSU and 265 V to 90 V for APU290.
— For expansion chassis power supply: The input supply voltage is in the
range -40 V to -72 V.
• Ensure that the wire size and dimension requirements are based on cable
length and local engineering standards and practices.
• Use only manual screwdriver for fastening of any circuit packs.
Note 1: Do not use any Power screwdriver for fastening of any circuit
packs.
Note 2: You must install the 6200 network element in a restricted access
location (RAL) in accordance with EN60950.