Preparing for installation and commissioning 4-5
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Requirements
To commission an 6200 network element you must have the following
information:
network diagrams that describe 6200 paths
network element type for each network element in the 6200 network
system timing diagram which shows building integrated timing supply
(BITS) sources
fiber numbers and patch panel connections for each fiber path
Test equipment
Equipment used for measurement must be pre-calibrated by an approved test
facility.
Table 4-3 lists the test equipment to be used.
pliers
safety glasses
socket/wrench set, 1/2 in. drive
socket, 3/8 in. hexagonal 3 in. deep—for M-10, standard anchoring
socket, 5/8 in. hexagonal 3 in. deep—for M-12, earthquake anchoring
socket, 8 mm
socket, 10 mm
spirit level, 24 in.
tape
tin snips
torque wrench
wire cutters
Table 4-2 (continued)
Tools and materials list
Tool or material