4-4 Preparing for installation and commissioning
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Tools and materials list
Make sure that you have the tools listed in Table 4-2 before you go to the site
to install an 6200 network element. This list does not include items that are
ordered by the customer or that are part of the shipment.
Table 4-2
Tools and materials list
Tool or material
#6 AWG (16 mm2) 7-strand copper insulated conductor ground
wire (as required)
16 mm drill bit (for seismic zone 2) or
18 mm drill bit (for seismic zone 4)
cable ties
claw hammer
crimping tool
digital voltmeter (DVM)
ESD heel grounder
ESD vacuum
miniature screwdriver
ESD wrist strap
felt marker
flathead screwdriver
frame leveling kit-NT7E6040 (as required)
frame mover
gloves
hammer drill
ladder
masonry drill
no-oxide paste
nut driver, 5/16 in.
nut driver, 10 mm
Manual Phillips screwdriver