System testing 7-49
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Procedure 7-10 (continued)
Testing 64G PKT SW circuit pack
Action
Step Action
1 Connect the test equipment and the 6200 network element as shown in
Figure 7-10 on page 7-50
2 Set all the ports to dot1q mode.
3 Create one Flow Point Template with FPCR for the CVLAN range 10 to 10.
4 Consider Ports P1, P2, P3 and P4 as optical ports. Create two ELINE
services between the ports with the flow points as shown in the Figure 7-10
on page 7-50.
5 Feed dot1q frames with VLAN 10 and TPID 8100 at P1 through Ethernet Test
Set 1.
6 Monitor these frames at port P2 and record the data in Table 12-8 on page
12-8.
Verify that there are no frame drops in the traffic feed.
Note: Follow this procedure for testing both GE(o) and 10GE(XFP)
interfaces.
—end—