8-26 Network reconfiguration
6200 Packet-Optical Platform Installation, Commissioning, and Testing Procedures
Release 1.1 009-6200-201 Draft Issue 1
Copyright
©
2014 Ciena
®
Corporation September 2014
Procedure 8-9 (continued)
Adding a 6200 node into a MS-SPRing/BLSR configuration
Step Action
15 Check Section-Trace at the links.
16 Check for alarms at Node X, Node A and Node C.
17 Release Forced switch from Node A and Node C.
18 Apply a lockout of protection on one of the MS-SPRing/BLSR interfaces on
each of the nodes except Node X.
19 Update MS-SPRing/BLSR Ring Map on all nodes of the ring on the WUI.
20 Check for alarms at Node X, Node A and Node C.
21 Release lockout of protection on the MS-SPRing/BLSR interfaces.
22 Check the status of Node X, Node A and Node C.
—end—