Procedure 8-10 (continued)
Deleting an 6200 node from a MS-SPRing/BLSR configuration
Step Action
15 Apply a lockout of protection on one of the MS-SPRing/BLSR interfaces for
each of the nodes except Node X.
16 Update MS-SPRing/BLSR Ring Map on all nodes of the ring on the WUI.
17 Check for alarms at Node A and Node C.
18 Release lockout of protection on both MS-SPRing/BLSR interfaces.
19 Check the status of Node A and Node C.
—end—