Commissioning
2023-05 D111XXXXXX | 05 63
6 Commissioning
Commissioning must be carried out by a qualified electrician or by a person trained and instructed in
electrical matters. The effectiveness of the protective measures and the correct mechanical and
electrical installation must be checked by a qualified electrician.
Commissioning may only be carried out when all necessary internal covers are fitted and the housing is
completely closed.
Observe the national legal requirements and regulations during commissioning.
The correct mechanical installation is checked according to the following criteria:
The degree of protection of the housing is not reduced or removed
The charging system has a good optical condition
The specifications for the buried depth of the housing or the specifications for the mounting
height were complied with
The housing has a safe installation condition according to its installation version
The correct electrical installation is checked according to the following criteria:
All electrical components are functional and not damaged
All display elements of the charging system are functional, visible and can be read
The function of any installed residual current circuit breakers can be verified by pressing a
button
The function of any installed counters is available and readable
The function of the charging system can be verified by means of a charging process
The electrical installation was carried out in compliance with all safety and warning instructions
and the listed safety requirements
NOTE
The Annex of this manual contains a test protocol with which the necessary steps can be recorded,
written down and archived.