Installation
2023-05 D111XXXXXX | 05 59
5.8.3 Installation with concrete base
The installation site must be chosen so that the cables do not protrude onto the road and do not come
to rest between the kerb and the road.
Installation sequence
1. Check parts and installation material for completeness.
2. Dig the pit.
3. Insert chippings (filling height: 10 cm)
4. Create a flat support surface.
5. Place and align the concrete base.
6. Fill pipe in concrete base with fine sand.
7. Prepare CMS.
8. Insert CMS.
9. Mount the positioning aid.
10. Fill the pit with excavated material (up to 10 cm).
11. Fill fine sand between pipes of concrete base and CMS.
12. Tighten the fastening screws.
13. Align the pipes of the CMS vertically.
14. Compress the filling material.
15. Fill the pit with excavated material (up to 30 cm).
16. Align the pipes of the CMS vertically again.
17. Compress the filling material.
18. Fill the pit with excavated material (up to 60 cm).
19. Compress the filling material.
20. Check the alignment.
21. Remove positioning aid.
22. Insert paving stones (cover layer) and adapt to pipes.