Installation and Operation Manual for RPI M50A
11 Maintenance
11. Maintenance
DANGER
Risk of death by electrocution
Potentially fatal voltage is applied to
the solar inverter during operation. This
potentially fatal voltage is still present
for 10 seconds after all power sources
have been disconnected.
Never open the solar inverter.
Always disconnect the solar inverter
from power before installation, open
the AC/DC isolating switch and
make sure neither can be acciden-
tally reconnected.
Wait at least 10 seconds until the
capacitors have discharged.
WARNING
High electrocution
When you remove the cover from the
fuse section, protection degree is no
longer IP65.
Remove the cover only when it is
really necessary.
Do not remove the cover when it is
raining and the inverter is wet.
Close the cover tightly after work.
In order to ensure the normal operation of the solar
inverter, please check it regularly at least once every
6 months. Check that all the terminals, screws, cables
are securely in place. If there are any damaged parts,
please contact a qualied technician to repair it or
to replace it with a new spare part. To ensure that
no foreign contaminants enter the warm air outlets,
please have them cleaned every 6 months by quali-
ed technicians.
11.1 Regular maintenance
Every 6 months the following checkings should be
done.
Check string fuses. Measure the current by using
a current transducer.
Check fans.
Check air lters.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Delta RPI M50A_120 and is the answer not in the manual?

Delta RPI M50A_120 Specifications

General IconGeneral
BrandDelta
ModelRPI M50A_120
CategoryInverter
LanguageEnglish

Related product manuals