Installation and commissioning multi EA 5000
36
NOTICE
Settled condensation and temperature differences can damage individual com-
ponents of the basic module during commissioning.
¡ If there is any temperature difference between the storage location and the operat-
ing location, allow the analyzer system to acclimatize for at least one hour in the
room it will operate in.
Connecting power and gases
} Connect the power cable to the connection of the rear of the basic module.
} Connect the power plug to a grounded power outlet.
} Connect the supplied connection hoses to the pressure reducers of the gas supply
and the the O
2
and Ar gas connections on the rear of the device (media connections
of the rear of the device).
} Set the inlet pressure on the pressure reducers (600 kPa (6 bar)).
} Connect the computer and connect it to the basic module via the supplied USB cable.
} Connect further system components (detectors, sampling modules) to the basic
module.
ü The basic module is now ready for operation and can be switched on.
Figure20Media connections of the rear of the device
1 Power connection 2 USB port for computer
3 "O
2
" oxygen connection 4 "Ar" argon connection