CHAPTER 4
ETSI Configuration
Installing the Rack
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
4-18
Fujitsu and Fujitsu Customer Use Only
22 Is the equipment rack within the tolerance level specified in Step 21 [p. 4-17]?
If YES:
Go to Step 27 [p. 4-18].
If NO:
Continue with Step 23 [p. 4-18].
23 Loosen the floor mounting bolts and top mounting hardware, and adjust the equipment rack
using shims on the mounting hardware. All shims and adjustments must meet locally
acceptable guidelines. Shims are not supplied with the ETSI rack.
24 Retighten all mounting hardware.
25 Measure the vertical alignment of the 2200 mm (86.6 inches) equipment rack. Ensure vertical
alignment is to within 4.76 mm (0.1875 inches).
26 Is the equipment rack within the tolerance level specified in Step 25 [p. 4-18]?
If YES:
Continue with Step 27 [p. 4-18].
If NO:
Go back to Step 23 [p. 4-18].
27 Update office records according to local procedures.
This procedure is complete.
Revision 1, June 2009

Table of Contents

Related product manuals