CHAPTER 2
Core Configuration
Storing, Unpacking, and Inspecting Equipment
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
2-14
Fujitsu and Fujitsu Customer Use Only
12 Is there any noticeable damage to the rack after the bubble wrap is removed?
If YES:
Go to Step 16 [p. 2-14].
If NO:
Continue with Step 13 [p. 2-14].
13 Does the rack contain equipment (standard rack configuration)?
If YES:
Continue with Step 14 [p. 2-14].
If NO:
Go to Step 18 [p. 2-14].
14 Locate the serial numbers on the left side of each equipment shelf mounted in the rack.
Compare the serial numbers with the serial numbers on the shipping documents.
15 Do the serial numbers on the equipment and the shipping documents match?
If YES:
Go to Step 17 [p. 2-14].
If NO:
Continue with Step 16 [p. 2-14].
16 Notify the transportation company if the equipment was damaged or if an improper shipment
was received. DO NOT continue the installation of the equipment until the problem has
been corrected. After the problem is resolved, repeat this procedure beginning with Step 2
[p. 2-12].
17 Update office records according to local procedures.
18 Do you want to install the equipment rack now?
If YES:
Proceed to Section 2.5, Installing the Rack [p. 2-16].
If NO:
This procedure is complete.