CHAPTER 5
Extension Configuration
Storing, Unpacking, and Inspecting Equipment
5-5
FLASHWAVE 7500 Release 6.1
Equipment Installation
Fujitsu and Fujitsu Customer Use Only
FNC-7500-0061-200
Issue 1, May 2009
6 At the front-left or -right corner of the container (see Figure 5-2 [p. 5-5]), use a box cutter to
cut the container away from the equipment rack. Start cutting from the top of the shipping
container to the bottom.
7 After the shipping container is cut open, remove it from the equipment rack.
8 Inspect the rack thoroughly to ensure that it is not damaged.
9 Is there any noticeable damage to the rack?
If YES:
Go to Step 16 [p. 5-6].
If NO:
Continue with Step 10 [p. 5-5].
Note: The equipment rack should be completely covered with bubble wrap to prevent damage during
shipment.
10 At the side of the rack, use industrial shears to cut open the bubble wrap. Start cutting from
the bottom of the rack to the top.
WARNING:
Always cut at the side of the rack to avoid damaging the equipment. Standard
configuration racks are delivered prewired. Do not cut or disconnect any wires.
11
Carefully remove the bubble wrap from the rack.
Figure 5-2: Removing Shipping Container from an Equipment Rack
r1253_1
Revision 1, June 2009