DIRECTION 5750007-1EN, REV. 1 LOGIQ E10 BASIC SERVICE MANUAL
Chapter 8 Replacement Procedures 8 - 359
Functional Checks
Perform the following functional checks to confirm the system is operational before returning the system
to the customer.
NOTE: NOT ALL functional checks will have to be repeated, if the functional check was performed
when the previous Option was re-installed. If ONLY a particular Option was removed, perform
the functional checks for the Backplane replacement and that particular Option.
Table 8-370 Option Box replacement Functional Checks
See:
Section
Functional Check Debrief Script
4-2-3 Power ON/Boot Up
LOGIQ E10 Basic Service Manual, Direction
5750007-1EN, Rev. 1. Equipment passed all
required checks and is ready for use.
4-2-7 B-Mode Checks
4-2-7 System CFM and PWD Checks
4-2-7 Basic Measurements
4-2-4
Power SHUT DOWN
DO NOT POWER SHUT DOWN until ALL
functional checks have been performed
In addition: Perform the following Functional Checks if
the Option was disconnected from the Back Plane.