Setup and installation
7 Setup and installation
7.1 Requirements of the location, where the machine is to be installed
In or
der to be able to operate the machine trouble-free, efficient and ergonomi-
cally, the following conditions must be met:
Ensure that the work surface is sufficiently stable and has the proper load-
be
aring capacity
Provide sufficient light at the workstation
Ensure there is sufficient clearance for or from neighbouring workstations
That the free space in the processing direction is at least 500 mm larger than
the w
orkpiece length.
That the machine location provides enough space for the machine operator.
C
onsider the requirement of enough space for loading, working and
stacking of workpieces.
At least 2000 mm of free space to operate the machine in the working area
are required.
In order to maintain and operate the machine properly, it must be set up
a
t least 500 mm away from the wall, parallel to the work direction (measure-
ment X).
The machine may only be used in dry rooms, free from frost and not outside.
W
W + 500 mm
X
Fig. 18: Space requirement at the installation site

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Hammer A2-26 and is the answer not in the manual?

Hammer A2-26 Specifications

General IconGeneral
BrandHammer
ModelA2-26
CategoryPlaner
LanguageEnglish

Related product manuals