Constellation™ 2002 June 20
11-2
Things to Do First
Verify that the rack and all interfacing equipment grounding meets site
specifications. (Office and earth ground.)
Verify that all SMA connectors are properly in place and secured with
the proper torque (8 to 9 inch-pounds).
Verify that all other connectors are properly seated and secured.
Check for proper configuration and connection of DS1/DS3 interface
(enable/disable, line build-out and line coding).
Verify module options with the Sales Order Specific Information. This
is important if performing radio capacity changes.
Verify that the test equipment is in calibration.
With a test equipment, verify that the power output at the monitor port
is correct in accordance with the Sales Order documents.
Verify that the 100 MHz oscillator is within tolerance ± 300 Hz at the
REF MON port.
Do not turn up transmit power to accommodate
the far-end received signal level.
Overdriving the Power Amplifier will cause high
CBER and UBER at the far-end Receivers.