Harris Corporation Constellation™
Installation and Commissioning 4-27
INSTALLATION AND
COMMISSIONING
Figure 4-17: Receiver Assembly, front view
7. Transmitter Power Measurement
This procedure for measuring the transmitter power should be followed
for new installations and as part of the annual maintenance requirement.
Note that this is a new procedure and should be followed
from now on.
Note: To prevent damage to the
connectors, do not exceed 8 to 9
in-pounds of torque.
RF IN (from ACU)
IF OUT (to Modem)
Thumb screw
REF MON
Reference frequency test
point (100 MHz)
Test points for
aligning the
antenna
(See
page 4-33)
FAULT
(red LED)
ON LINE
(green LED)
RSL
GND
Handle
LO MON*
LO synthesizer test point
(2.060 to 2.160 GHz)
(For factory use only)