166
Series 8 C300 Controller User's Guide
Honeywell
R500
April 2017
6. Load C300 Controller Configuration
6.3. Load components from Project
Considerations
All illustrations used in the procedure are for example purposes only.
To load an IOLINK block, perform the following steps.
Step
Action
Result
1
Click desired IOLINK block icon in
Project tab.
Selects and highlights the component.
2
Click Tools > Load. Or, click the
load button in the toolbar.
Also, you can right click on the IOLINK
block icon to select Load.
The Load Dialog box appears.