10. Connect the serial port cable.
11. If removed,
install the secondary riser.
12.
Install the access panel.
13.
Install the server into the rack.
14.
Connect all peripheral cables to the server.
15.
Connect each power cord to the server.
16.
Connect each power cord to the power source.
17.
Power up the server.
18.
If removed, install the bezel.
The installation is complete.
Power supply options
Hot-plug power supply calculations
For hot-plug power supply specifications and calculators to determine electrical and heat loading for the server, see the
Hewlett Packard Enterprise Power Advisor website (
https://www.hpe.com/info/poweradvisor/online).
Installing a redundant hot-plug power supply
CAUTION: All power supplies installed in the server must have the same output power capacity. Verify that all
power supplies have the same part number and label color. The system becomes unstable and might shut down if it
detects
dierent power supplies.
CAUTION: To prevent improper cooling and thermal damage, do not operate the server unless all bays are
populated with either a component or a blank.