18. Install the server into the rack.
19. Connect all peripheral cables to the server.
20. Connect each power cord to the server.
21. Connect each power cord to the power source.
22. Power up the server.
23. If removed, install the bezel.
The installation is complete.
Upgrading 4LFF to 8LFF
Prerequisites
Before you perform this procedure, make sure that you have a T-10 Torx screwdriver available.
Procedure
1. If installed,
remove the bezel.
2.
Power down the server.
3.
Remove all power:
a.
Disconnect each power cord from the power source.
b.
Disconnect each power cord from the server.
4.
Disconnect all peripheral cables from the server.
5.
Remove the server from the rack.
6.
Remove the inner rack rails.
7.
Remove the access panel.
8.
Remove the inner drive cage blank.
Hardware options installation
73