9. Remove the fan wall covers.
10. Remove all the existing single rotor fans and fan blanks.
11.
Connect the signal and power cables for the 8LFF.
12.
Install eight dual rotor fans included in this 4LFF to 8LFF upgrade option.
13.
Install the air bale included in this 4LFF to 8LFF upgrade option.
14.
Install the inner drive cage.
15.
Install the access panel.
16.
Install the inner rack rails.
17.
Install the server into the rack.
18.
Connect all peripheral cables to the server.
19.
Connect each power cord to the server.
20.
Connect each power cord to the power source.
21.
Power up the server.
22.
If removed, install the bezel.
The installation is complete.
Upgrading 8SFF to 16SFF
Prerequisites
Before you perform this procedure, make sure that you have a T-10 Torx screwdriver available.
Procedure
1. If installed, remove the bezel.
2.
Power down the server.
3. Remove all power: