3. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
4. Disconnect all peripheral cables from the server.
5.
Remove the server from the rack.
6. Remove the access panel.
7. If energy pack is to be installed in 4LFF or 8SFF configurations,
install a fan in fan bay 7.
For more information about fan bay locations, see
Fan bay numbering.
8. Install the energy pack:
a. Insert the energy pack at an angle.
b. Push the release latch in backward direction.
c. Push the energy pack down from other end.
d.
Connect the energy pack cable and secure the extra length of the cable in the clip.
9.
Connect the controller backup power cable.
10. Install the access panel.
11.
Install the server into the rack.
12. Connect all peripheral cables to the server.
13. Connect each power cord to the server.
14. Connect each power cord to the power source.
15.
Power up the server.
16. If removed,
install the bezel.