Step 2 Install the pipe adapter and seal the adapter using sealant, as shown by 2 in
Figure 3-29.
Step 3 Wrap the pipe with heat insulation cotton and install the pipe and hoop, as shown
by 3 in Figure 3-29.
----End
Example
A
humidier water inlet pipe and a condensate pump drainpipe are routed from
the bottom or top. You can route the pipes based on site requirements.
When routing pipes from the top, do not route the pipes over servers. If
unavoidable, take protective measures to protect the servers from being
aected
by pipe leakage.
Do not remove the humidier water inlet pipe to prevent sealing fault between
water inlet pipe and the humidier cylinder.
The humidier water inlet pipe is a hose installed under the humidier. When
connecting the hose, straighten the hose and secure it with cable ties.
The top and bottom pipe routing methods are the same with that of self-
drainpipes. Figure 3-30 and Figure 3-31 respectively show top and bottom pipe
routing.
NetCol5000-A(025, 035) In-row Air Cooled Smart
Cooling Product
User Manual (600 mm Width) 3 Installation Guide
Issue 17 (2020-10-22) Copyright © Huawei Technologies Co., Ltd. 58